Project Management Dashboard
The Project Management dashboard provides a comprehensive view for project managers and executives overseeing project delivery. It focuses on overall project health, milestone progress, and risk management.
Access: Navigate to /dashboards/project-management
Overview Metrics
| Metric | Description |
|---|---|
| Estimated Completion | Days until project completion with schedule variance indicator |
| Task On-Time Completion | Percentage of tasks closed by their due date |
| Weekly Task Velocity | 3-week rolling average of tasks completed per week |
| Open High Risk Items | Count of open high-priority risks and issues |
Widgets
Milestone Status
The Milestone Status widget shows progress for each project milestone:
- Progress Ring - Visual completion percentage with color coding
- Milestone Name - The milestone title
- Due Date - Target completion date
- Status Colors - Green for on-track, orange for at-risk, red for overdue
This widget provides at-a-glance visibility into milestone health across your project.
Tasks Remaining Chart
The burndown chart helps track project progress over time:
- Solid Line (Actual Remaining) - Current number of open tasks
- Dashed Line (Expected Remaining) - Ideal trajectory based on tasks due by each date
- Summary Stats - Total tasks, actual remaining, expected remaining
When the actual line is above the expected line, the project is behind schedule. When below, you're ahead of schedule. The burndown chart is essential for identifying schedule risk early.
Activity Timeline
Shows recent project events:
- Period Grouping - View activities by day, week, or month using the dropdown
- Period Navigation - Use arrow buttons to move between time periods
- Entity Filter - Filter by organization, team, or individual members
- Date Picker - Jump to a specific date
- Event Types - Task updates, comments, status changes, assignments, and more
The timeline displays activities with contextual icons showing what type of change occurred (created, updated, status changed, etc.).
Closed Issues per Team
A radial chart showing task distribution across teams. Use this to understand which teams are handling the most work and identify potential imbalances.
Open Approvals
A list of items awaiting approval decisions. Helps identify bottlenecks in the approval process.
Risk Register
A table of identified risks with status and mitigation plans. Critical for proactive risk management.
Decisions
A log of project decisions and their outcomes. Maintains a record of key choices made during the project.
Understanding the Metrics
Estimated Completion
This metric predicts how many days until project completion based on:
- Current task progress - How many tasks are open vs closed
- Weekly velocity - How fast tasks are being completed
- Due date distribution - When remaining tasks are expected to be done
A positive variance means you're ahead of schedule; a negative variance means you're behind.
How It's Calculated:
- Count total open tasks
- Calculate average weekly completion rate (velocity)
- Divide open tasks by velocity to estimate weeks remaining
- Compare against original project timeline
Task On-Time Completion
This percentage shows how often tasks are completed by their due date:
- Numerator - Tasks closed on or before their due date
- Denominator - Total closed tasks that had due dates
| Percentage | Interpretation |
|---|---|
| 90%+ | Excellent on-time delivery |
| 80-89% | Good, but room for improvement |
| 70-79% | Needs attention - investigate causes |
| Below 70% | Critical - address immediately |
Weekly Task Velocity
Velocity measures team productivity using a 3-week rolling average. This smooths out weekly variations to show sustainable pace.
Open High Risk Items
Count of open items marked as high priority or high risk, including:
- Tasks with "High" priority
- Issues blocking other work
- Risks without mitigation plans
- Overdue items from key milestones